STOWAGE BOX MAINTENANCE - Continued 
1.	 	 Remove second deck flooorboard from the outside edge of trailer directly above stowage box being 
removed per WP 0061 00-1. 
2.	 	 Remove eight locknuts (1), screws (4), washers (3), rubber washers (2), and stowage box (12) from trailer 
frame. Discard rubber washers and locknuts. 
STOWAGE BOX COMPONENTS REPLACEMENT 
1. Stowage box components (6, 7, 10, and 11) are removed by removing the locknuts (9), washers (8), and 
screws (5) holding the item in place. Discard locknuts. 
2.	 Components (6, 7, 10, and 11) are installed by attaching the new item to the stowage box (12) with 
screws (5), washers (8) and new locknuts (9). 
INSTALLATION 
1.	 Install stowage box (12), eight screws (4), washers (3), new rubber washers (2), and new locknuts (1). 
Torque per WP 0088 00-1. 
2. Install deck floorboard removed per WP 0061 00-2. 
12 
1 
5 
2 
8 
11 
9 
10 
8 
9 
8 
9 
3 
8 
4 
5 
6 
5 
7 
Figure 1. Stowage Box 
FOLLOW ON TASKS 
	 Replace BII items in stowage box and secure. 
END OF WORK PACKAGE 
0058 00-2 
 | 
			||
![]()  | 
		||