G VALVE REPLACEMENT
THIS WP COVERS:
Removal, Installation, Follow-On Tasks
INITIAL SETUP:
Maintenance Level
Tools and Special Tools
Organizational
Tool kit, general mechanic's (item 4, WP 0156 00)
Suitable container (item 1, WP 0156 00)
Materials/Parts
Equipment Conditions
Seals (4) (item 80, WP 0160 00)
Self-locking nuts (16) (item 87, WP 0160 00)
Semitrailer disconnected from prime mover (refer
to WP 0007 00)
References
Semitrailer grounded (refer to WP 0007 00)
Semitrailer fuel tank drained (refer to WP 0007 00)
Negative terminal disconnected from battery (refer
to WP 0007 00)
REMOVAL
NOTE
Place suitable container under G valve prior to removal.
It may be necessary to loosen piping control components
(refer to WP 0122 00) prior to removal of G valve.
Remove 8 self-locking nuts (1), 16 washers (2), 6 bolts (4) and 2 studs (6), 2 seals (5), and valve (3).
Discard self-locking nuts and seals.