6-30. MANIFEST BOX REPLACEMENT.
This Task Covers:
a. Removal
b. Installation
c. Follow-On Tasks
Initial Setup:
Tools and Special Tools:
Tool kit, general mechanic's (Item 4, Appendix B-3)
Equipment Conditions:
Landing legs down
Semitrailer disconnected from prime mover
Tires chocked
Ground boards emplaced
General Procedure:
a. Removal.
Remove four locknuts (3), washers (2), bolts (4), and document box (1) from semitrailer. Discard
locknuts.
b. Installation.
Install document box (1), four bolts (4), washers (2), and new locknuts (3).



 