Tweet |
Custom Search
|
|
|
||
TM 9-2330-326-14&P
This Task Covers:
a. Removal
b. Installation
c. Follow-On Tasks
Initial Setup:
Tools and Special Tools:
Equipment Conditions:
Tool kit, general mechanic's (Item 4, Appendix B-3)
Landing legs down
Semitrailer disconnected from prime mover
Tires chocked
Ground boards emplaced
WARNING
Chock tires to prevent trailer movement.
NOTE
There are two dock bumpers and four suspension stops and they
are removed and installed the same way. The following procedure
covers either one dock bumper or one suspension stop.
General Procedure:
a. Removal.
Remove four locknuts (1 or 5), four bolts (4 or 8), four washers (3 or 7), and bumper (2 or 6). Discard
locknuts.
b. Installation.
Install bumper (2 or 6), four washers (3 or 7), four bolts (4 or 8), and four new locknuts (1 or 5).
|
||