General Procedure:
a. Removal.
1.
Loosen jamnut (5). Remove cotter pin, pin, yoke assembly (4) and jamnut. Replace cotter pin.
2.
Remove two locknuts (3), two washers (2), and air brake chamber (1). Discard locknuts.
b. Installation.
1.
Install air brake chamber (1), two washers (2), and two new locknuts (3).
2.
Install jamnut (5), yoke assembly (4), pin, and new cotter pin. Tighten jamnut.
c.
Follow -On Tasks.
1.
Connect semitrailer to prime mover.
2.
Remove tire chocks.
3.
Raise landing legs.
4.
Remove/store ground boards.
5.
Pressurize system.
6.
Check system for air leaks.
7.
Road test to check for safe opeation.